GENERAL
1.1 Description
The work of this section includes the supply and installation of gypsum
board as indicated and as specified herein.
Extent of work to be expanded, if
necessary, to suit project requirements.
Include also (water-resistant gypsum
board)(abuse-resistant gypsum board)(glass mat tile backer
board)(reinforced cementitious board) (glass mat gypsum sheathing
board).
Include also the sealing of perimeter joints gypsum board sound rated
partitions and supply and installation of acoustical insulation in
gypsum board sound rated partitions (mineral wool insulation within fire
rated partitions
Delete items not applicable, or
amend to suit project requirements.
Grouting of pressed steel door frames in
gypsum board partitions.
Delete if not applicable to the
project.
Installation of access panels in gypsum
board partitions.(ceilings)
Delete if not applicable to the
project or amend to suit project requirements.
1.2 Related Work Under Other Sections
Temporary Heating and Ventilation by the Contractor under Division 1 –
General Requirements.
Wind Bearing Steel Studs: Section 05410
Interior Steel Studs and Furring: Section 09110
Lathing and Metal Furring: Section 09205
Interior Plastering: Section 09210
Stucco: Section 09220
Gypsum Shaft Wall Systems: Section 09260
Sprayed Textured Finish: Section 09290
Supply of Access Panels: Division 15 (and 16).
Extent of related work to be
deleted or expanded to suit project requirements.
1.3 Quality Assurance – Standard
Specifications
Section 9.6 – Gypsum Board of the Association of Wall and Ceiling
Contractors (A.W.C.C.) Specification Standards Manual, together with
authorized additions and amendments, shall be used as a reference
standard and shall form part of this project specification.
Where modifications to the Standards contained within the A.W.C.C.
Specification Standards Manual are included in this project
specification, then the Standards shall govern in case of conflict.
The installer of gypsum board shall keep a copy of Section 9.6 – Gypsum
Board of the A.W.C.C. Specifications Standards Manual available at the
project site for reference purposes.
All gypsum board products and accessories to be used in the project
shall meet or exceed the requirements specified under Part 2 – Products
of Section 9.6 of the A.W.C.C. Specification Standards Manual. The
proposed product manufacturer shall provide the Consultant, if
requested, with satisfactory evidence indicating conformance of his
products with the requirements specified in the A.W.C.C. Specification
Standards Manual. Any product failing to meet those requirements will be
rejected by the Consultant.
Reference in these project specifications to Section numbers, Parts and
Item Numbers means those Sections, Parts and Items contained within
Section 9.6 of A.W.C.C. Specification Standards Manual.
Products and installation shall be in Metric (Imperial) measurement as
specified under Section 9.6 of the A.W.C.C. Specification Standards
Manual.
Delete Metric or Imperial, as
applicable for the Project.
1.4 Qualifications
The Gypsum Board Contractor shall have proven satisfactory experience in
the type of work included in this section and shall, if requested by the
Consultant provide proof of such experience.
The Gypsum Board Contractor shall be a member in good standing of a
recognized association of the Wall and Ceiling industry and shall, if
requested by the Consultant, provide proof of such membership.
Only mechanics skilled in the trade(s) required by this section and
having either a Red Seal Inter-Provincial trades qualification or a
Provincial trades qualification, or be a registered apprentice in the
applicable trade shall be engaged in the work. If requested by the
Consultant the Gypsum Board Contractor shall provide a list of the
trade(s) showing their qualification certificate of proficiency.
1.5 Product Delivery/Storage/Handling
Deliver and store material undamaged in original wrapping or containers,
with manufacturer’s labels intact.
Prevent damage to materials during handling and storage. Keep gypsum
board and other materials under cover and free from dampness.
1.6 Job Conditions
Ensure temperature and ventilation conditions are maintained as required
under Section 9.6 – Part 3, Item 2.
Protect work of other sections from damage resulting from work of this
section.
Take necessary protection to avoid spattering of surfaces adjacent to
gypsum board, particularly aluminum and glass. Spatters from this work
shall be promptly removed from adjacent surfaces.
Examine the underlying visible surfaces and adjoining work and report
defects at time of installation that might impair the gypsum board to
the Contractor in writing.
For cutting of reinforced cementitious boards with mechanical devices,
workers shall wear protective masks to prevent inhalation of airborne
dust in accordance with WCB regulations.